Route Construction for Ethylene Transmission Pipeline | 24 inch | Western Iran

Client: Petrochemical Industries Company

Project Completion Date: Mordad 1384

Route Type: 65% rocky

Pipeline Length: 176 km

Route Construction Volume: 6,500,000 m³

Client: Iran Gas Engineering and Development Company

Project Completion Date: Khordad 1393

Route Type: 90% rocky

Pipeline Length: 49 km

Route Construction Volume: 3,000,000 m³

Client: National Iranian Gas Company

Project Completion Date: Shahrivar 1382

Route Type: 70% rocky

Pipeline Length: 56 km

Route Construction Volume: 2,000,000 m³

Client: Iranian Oil Pipelines and Telecommunication Company

Project Completion Date: Dey 1391

Route Type: 60% rocky

Pipeline Length: 73 km

Route Construction Volume: 1,200,000 m³

Client: Iran Gas Engineering and Development Company

Project Completion Date: Dey 1388

Route Type: 50% rocky

Pipeline Length: 72 km

Route Construction Volume: 1,000,000 m³

Client: National Iranian Gas Company

Project Completion Date: Mehr 1385

Route Type: 10% rocky

Pipeline Length: 110 km. During execution of the “24-inch North Ahvaz Gas Transmission Pipeline” project, two crossings beneath the Shatit and Gargar Rivers (branches of the Karun River) were completed using the HDD method.

Client: National Iranian Gas Company

 Project Completion Date: Tir 1386

Route Type: 60% rocky

Pipeline Length: 40 km

Client: National Iranian Gas Company

 Project Completion Date: Aban 1377

 Route Type: 50% rocky

 Pipeline Length: 65 km

Client: National Iranian Gas Company

Project Completion Date: Ordibehesht 1382

Route Type: 70% rocky

Pipeline Length: 26 km

 Route Construction Volume: 500,000 m³

Client: National Iranian Gas Company

Project Completion Date: Bahman 1367

Route Type: 10% rocky

Pipeline Length: 27 km

Route Construction Volume: 300,000 m³

Client: Bushehr Province Gas Company

Project Completion Date: Dey 1391

Route Type: earth terrain

Pipeline Length: 20 km

Route Construction Volume: 50,000 m³